Finishes
HVAC
Plumbing
Fire Sprinkler
Electrical
- 1. Main Entrance & Elevator Lobby Including
Wall/Floor/Ceiling Finishes
- 2. Electric/Mechanical Equipment Rooms
- a. Floor- Concrete Troweled (unfinished)
- b. Walls- Painted Drywall
- c. 3'-0" x 8'-0" Painted Hollow Metal Doors/Frames
- 3. Telephone/Janitor Rooms
- a. Floor- Concrete Troweled (unfinished)
- b. Walls- Painted Drywall
- c. 3'-0" x 8'-0" Finished Wood Doors/ Hollow Metal
Frame
- 4. Stairwells/Vestibule
- a. Floor- Sealed Concrete Treads/Landings
- b. Walls- Painted Drywall
- c. 3'-0" x 8'-0" Finished Wood Door/HM Frame
@ Corridor
- d. Code signage
- 5. Restrooms sized to meet code
- a. Floor/Base- Ceramic Tile
- b. "Wet" Walls- Ceramic Tile
- c. "Non-Wet" Walls- Vinyl Wall Covering (VWC)
- d. Ceiling- Painted Drywall w/ Recessed Light Cove
- e. Entry Doors- 3'-0" x 8'-0" Finished Wood Doors/ HM Frame
- f. Lavatory Countertops- Stone
- g. Toilet Partitions/Accessories
- h. Mirrors over Countertops
- i. Code signage
- 6. 1st Floor Corridors required for code required existing
- a. Floor- Carpet
- b. Base- Finished Wood
- c. Walls- VWC
- d. Ceiling- 2' x 2' Acoustical Ceiling and Grid
- 7. Fire Command Center (1st floor)
- a. Floor- Concrete Troweled (unfinished)
- b. Walls- Painted Drywall
- c. 3'-0" x 8'-0" Painted Hollow Metal Doors/Frames
- 8. Tenant Areas outside of Building Core Rooms
- a. Floor - Troweled Concrete
- b. Floor to floor height of 14' p
- c. Exterior Window Blinds- 1" horizontal Levelor Riviera or equal
- 1. Base System
- a. Water Cooled Floor by Floor DX Air Handler Units
- b. Cooling Towers and Water Pumps (located on the roof or ground)
- c. Condenser Piping distribution (from roof or ground to individual floors)
- d. EMS- DDC Controls for Shell HVAC systems
- 2. Building Core Area (1st Floor Elev. Lobby, Restrooms, Elect./Mech., Corridors)
- a. All Ductwork and VAV distribution
- b. Ceiling registers, grilles, diffusers, EMS req'ts
- c. Toilet Exhaust Ventilation
- 3. Tenant Areas outside of Building Core
- a. Main Duct loop (medium pressure) distribution
- b. Return Air Plenu
- c. Smoke Control @ Stairwells
- 1. Core Restroom Fixtures (urinals, water closets, lavatories)
- 2. Mop Sink inside Janitor's Closet
- 3. Waste/Vent Stack for Future TI's
- 4. Wet Stack for future TI's
- 1. Building Core Area (Elev. Lobby, Restrooms, Corridors)
- a. Drywall Ceiling- Fully recessed heads
- b. Acoustical Ceiling- Semi-recessed heads
- 2. Tenant Areas outside of Building Core
- a. Upright heads spaced @ 225 SF/head
- 1. Power
- a. General Power Design: 5 Watts/USF (Exc. HVAC)
- b. Lighting Power Design: 2 Watts/USF
- c. Emergency Generator for Life Safety Req'ts
- d. Transformer/floor for (120/208V) Panels w/breakers
for convenience
Req'ts (per floor)
- e. (277/480V) HVAC Panels w/ breaker (per floor)
- f. (277/480V) Lighting Panel w/s breaker (per floor)
- g. Electrical distribution for shell only power,
mechanical, and lighting
- 2. Lighting
- a. Restrooms: Can Lights
- b. Restroom Alcove: Recessed Downlight
- c. 1st Floor Elev. Lobby: Recessed Cove Lighting
- d. Elect/Telephone/Mech. Rooms: Chain hung
fluorescent fixtures
- 3. Fire Alarm System
- a. Fire Alarm Control Panel (FACP) with Graphic Annunciator
Panel located at the 1st Floor Main Lobby
- b. Manual pull stations at exits/ stairs
- c. Core Area- Code req'd smoke detectors, pull stations, strobes
- d. Smoke Detectors for Shell provided Mech. Equipment
- 4. Telephone System
- a. Copper riser cables to each Telephone Room (1 per floor)
- 5. Security
- a. Access Control to Parking Garage